A Columbia paper for Brookings estimates $10.3T of AI infrastructure spending from 2025 to 2032. Here's how it's being financed, and why risk is harder to see.

In this article
  1. The size of it
  2. Where the money comes from
  3. The template: Meta's Hyperion
  4. Why that matters
  5. What to watch

Everyone talks about how much AI costs. Fewer people ask who's lending the money, and where that debt sits. A paper by Columbia Business School's Stijn Van Nieuwerburgh, presented at Brookings in September 2026, maps it out. This piece is about the financing structures. For whether the spending pays back, see the AI bubble capex math.

The size of it

From Brookings' Oct 8, 2026 summary:

  • U.S. AI investment in data centers, power and chips could total $10.3 trillion from 2025 to 2032.
  • That's 3.63% of GDP per year on average.
  • For comparison, he puts the railroad boom at about 2.2% of GDP at its peak (about 1870 to 1890), highways at about 1.1% in the 1950s, and the telecom and fiber boom at about 1.1%.

On the Brookings podcast, host Aaron Klein noted that companies like Meta and Microsoft are now spending more on AI than they generate in operating cash flow. That gap is what the financing fills.

Where the money comes from

The paper says a growing share of capital comes from outside the big tech companies: real estate developers, infrastructure funds, private credit and structured finance vehicles. "In many cases, the user of compute is not the owner of the underlying assets."

The main tools:

  • Leases. The tech company rents the building instead of owning it.
  • Joint ventures. A partner buys most of the project's equity.
  • Private credit. Loans from funds, not banks or public bond markets.
  • Special-purpose vehicles (SPVs). A separate company whose only asset is the data center (or the chips) and which borrows against it. More in our SPV explainer.

The template: Meta's Hyperion

The paper uses Meta's Hyperion campus in Richland Parish, Louisiana:

  • Meta sold an 80% equity stake to private credit firm Blue Owl for about $2.5B.
  • The joint venture, Beignet, raised $27B of debt in October 2025, rated A+ by S&P, one notch below Meta.
  • That's about 90% debt ($27B against roughly $30B of asset value), far above a typical investment-grade company.

On the podcast, Van Nieuwerburgh explained the leases: Meta signed five consecutive 4-year leases, and it can walk away every four years, but then owes a residual value guarantee (a payment) to the structure. Only the current lease shows up on Meta's balance sheet. The future leases don't, until they start.

Why that matters

His point isn't that the deal is bad. He said that as long as Meta doesn't go bankrupt, Hyperion should generate enough cash to repay the debt. The concern is visibility:

  • Leverage sits in the SPV, so the tech company "looks like it's relatively under-leveraged."
  • Lease and consolidation decisions are "judgment-heavy."
  • If a tenant leaves and nobody else wants a GPU facility, the loss falls on the landlord and lenders.
  • Hyperscalers still bear a lot of risk because they usually own the IT gear inside.

He draws a cautious parallel to pre-2008 off-balance-sheet bank vehicles, which ended up back on balance sheets. Brookings' summary: "premature to call this systemic risk," but "better measurement and disclosure should come while the industry's capital structure is still evolving."

What to watch

When Big Tech reports next week (dates and lines), look past capex. Check lease commitments, guarantees and joint-venture disclosures in the notes. NVIDIA's guarantee of up to $105B for a campus leased to OpenAI (NVIDIA preview) is the same theme.

FAQ

How much will the AI build-out cost?

Van Nieuwerburgh's central estimate, summarized by Brookings on Oct 8, 2026, is $10.3 trillion from 2025 to 2032 in the U.S., or 3.63% of GDP per year. It's a projection, not a tally of money already spent.

What is off-balance-sheet financing?

It's when a company uses an asset (like a data center) without owning it or carrying the related debt on its own balance sheet. A separate entity owns the asset and borrows against it, and the company leases it.

What was the Hyperion deal?

Per the paper, Meta sold an 80% equity stake in its Hyperion data center project in Louisiana to private credit firm Blue Owl for about $2.5B. The joint venture, Beignet, raised $27B of debt in October 2025 against roughly $30B of asset value.

Is this a bubble?

The paper doesn't say so. Brookings' summary says it's 'premature to call this systemic risk,' while arguing for better disclosure.

Sources

  1. Brookings, “The $10 trillion question: Financing the AI buildout” (Oct 8, 2026)https://www.brookings.edu/articles/the-10-trillion-question-financing-the-ai-buildout/
  2. Columbia Business School, Financing the AI Build-Out (Stijn Van Nieuwerburgh)https://business.columbia.edu/faculty/research/financing-ai-buildout-0
  3. Stijn Van Nieuwerburgh, “Financing the AI Build-Out” (draft paper, Mar 19, 2026)https://business.columbia.edu/sites/default/files-efs/imce-uploads/svannieuwerburgh/papers/FinancingAIBuildout_03192026.pdf

Newsletter

The Codema publication. Consent is required. You are not subscribed until you confirm from the email, and nothing is stored if email delivery is not connected.