AI data centres and the power grid: what the IEA numbers actually say

TechTech

AI data centres and the power grid: what the IEA numbers actually say

High-voltage transmission towers and power lines crossing open country under a cloudy sky
Photo by Brett Sayles on Pexels

Data centres used about 485 TWh in 2025 and could hit 950 TWh by 2030, says the IEA. Here's what that means, what's driving it and where the grid pinches.

In this article
  1. The headline numbers
  2. Per query, AI is getting much cheaper
  3. Where the grid actually pinches
  4. Workarounds operators are using
  5. What the IEA does not say
  6. Why builders should care

"AI is going to break the grid" is everywhere right now. The International Energy Agency (IEA) has the most cited numbers on this, so here's what they say, without the hype.

The headline numbers

From the IEA's Key Questions on Energy and AI, published Apr 16, 2026:

Figure
Data centre electricity use, 2025 ~485 TWh
Growth in 2025 +17%
Growth for AI-focused data centres, 2025 +50%
Central projection for 2030 ~950 TWh, around 3% of global electricity demand
AI-focused data centres, 2025 to 2030 roughly triple

For scale, the IEA's 2025 report put 2024 data centre use at 415 TWh, or about 1.5% of the world's electricity. It said the 2030 level would be slightly more than Japan's total electricity use today.

Per query, AI is getting much cheaper

This is the part that rarely makes the headline. The IEA says energy use per AI task has dropped by at least an order of magnitude a year recently. A simple text query now typically uses less electricity than running a TV for the same amount of time.

So why is total demand rising? Because usage and the type of work are changing. The IEA says video generation, reasoning and agentic tasks can use hundreds or thousands of times more energy per query than simple text generation. If you build agents that loop for minutes, you're on the expensive end of that range. (Our guide to running coding agents safely is about permissions, but it's the same kind of long-running work.)

Where the grid actually pinches

The bottlenecks are physical, not just about electricity in general:

  • Grid connections and equipment. The 2026 report says supply chains for gas turbines, transformers, advanced chips and IT parts have tightened. In its press release, the IEA says project pipelines are straining planning systems and holding up grid connections.
  • Delays. The 2025 report estimated that, unless those risks are addressed, around 20% of planned data centre projects could be delayed. It said new transmission lines can take four to eight years in advanced economies.
  • Concentration. Data centres cluster. The 2025 report said nearly half of US data centre capacity sits in five regional clusters, which is why local grids feel it far more than the global share suggests.
  • Rack density. By 2027, a single advanced server rack could have peak demand equal to 65 households, per the 2026 report. AI server power density rose 11x between 2020 and 2025.

Workarounds operators are using

  • Onsite gas. In the US, developers are pushing projects with onsite gas generation. The IEA estimates around 15–27 GW of onsite gas may power data centres by 2030, and says reliable onsite supply needs 30–70% overbuild relative to demand.
  • Batteries. About 20–25 GW of battery storage could be installed in data centres globally by 2030, which could make them a grid asset if the incentives line up.

What the IEA does not say

It doesn't say AI is the biggest driver of new electricity demand worldwide. In 2025 it said data centres are about one-tenth of global demand growth to 2030, behind industrial motors, air conditioning and EVs. In advanced economies, though, where demand had been flat for decades, data centres are more than 20% of growth.

Why builders should care

Power is now part of the cost of compute. It shows up in GPU rental prices, in the memory shortage the IEA also flags (it says the HBM shortage should last through at least the end of 2027), and in how fast new capacity like NVIDIA's DSX POD can actually switch on.

FAQ

How much electricity do data centres use?

About 485 TWh in 2025, per the IEA's Key Questions on Energy and AI report (Apr 16, 2026). In its 2025 report, the IEA put 2024 use at 415 TWh, around 1.5% of global electricity.

Will AI double data centre power use?

The IEA's central case has total data centre consumption roughly doubling to 950 TWh by 2030, with AI-focused data centres tripling. It flags near-term bottlenecks and possible upside after 2030.

Does one ChatGPT-style query use a lot of power?

The IEA says simple text queries now typically use less electricity than running a TV for the same time. Video generation, reasoning and agent tasks can use hundreds or thousands of times more per query.

Is AI the biggest driver of electricity growth?

Not globally. In its 2025 report, the IEA said data centres are around one-tenth of global demand growth to 2030, behind industrial motors, air conditioning and EVs. In advanced economies, they're more than 20% of growth.

Sources

  1. IEA, Key Questions on Energy and AI: Executive summary (Apr 16, 2026)https://www.iea.org/reports/key-questions-on-energy-and-ai/executive-summary
  2. IEA, “Data centre electricity use surged in 2025, even with tightening bottlenecks driving a scramble for solutions” (Apr 16, 2026)https://www.iea.org/news/data-centre-electricity-use-surged-in-2025-even-with-tightening-bottlenecks-driving-a-scramble-for-solutions
  3. IEA, Energy and AI: Executive summary (Apr 2025)https://www.iea.org/reports/energy-and-ai/executive-summary

Newsletter

The Codema publication. Consent is required. You are not subscribed until you confirm from the email, and nothing is stored if email delivery is not connected.